750,000
metric tons of aluminum per year
OPA’s stated production capacity.
Source: OPA · Sept 23 (opens in a new tab)
A grassroots campaign · Inola, Oklahoma
The largest aluminum smelter in the United States is proposed three miles from our schools, our herds, and the Verdigris River. We are the people who live here. We intend to keep this place.
from Inola High School to the proposed smelter site
01 — What’s proposed
Oklahoma Primary Aluminum wants to build a 441-acre primary aluminum smelter at the Port of Inola. These figures describe the developer's proposal, not approved limits.

750,000
OPA’s stated production capacity.
Source: OPA · Sept 23 (opens in a new tab)441
The site footprint described in OPA’s release.
Source: OPA · Sept 23 (opens in a new tab)0.64
Proposed maximum potline cap, not an approved limit or whole-facility annual total.
Source: OPA · Sept 3 (opens in a new tab)1,000+
1.5 million tons of alumina powder moved upriver annually, according to the application.
Source: Permit application (opens in a new tab)02 — The questions
On October 7 the Oklahoma DEQ asked the developer to substantiate its emissions calculations. The review is ongoing. These are the questions still open.
DEQ asks for evidence supporting the emissions model and air-quality analysis behind the proposed fluoride cap.
DEQ told the Journal Record in August that its review will weigh how fluoride settles on vegetation and livestock.
OPA says it is negotiating with PSO. A final power agreement and the impact on customer bills remain undetermined.
The site sits within the reservation. The Nation formally opposed the smelter in July and says it was never consulted.
03 — The public record
· Tulsa Ports board
The suit would target the moratorium and ordinances limiting development at the port. Authorization is not a filing or a ruling; FOX23 had not confirmed a filing as of Oct 15.
Read the FOX23 report (opens in a new tab)· Oklahoma DEQ
DEQ frames this as normal technical review, not a rejection. The air permit remains under review.
Read KJRH’s report (opens in a new tab)· Public Radio Tulsa
OPA says more analysis is coming. Its PSO power agreement is not final.
Read the coverage (opens in a new tab)· OPA release
The developer’s public description of scale, site, and capacity. These are proposed figures.
Read the release (opens in a new tab)Official status, checked October 19, 2026 — DEQ lists the air application as under review. BACT, modeling and draft-permit meetings are listed as TBD. Check official notices for deadlines.
04 — Stand with Inola
Protect Inola directs supporters to Barrow & Grimm for the legal fight. One call, one shared link, one more neighbor informed moves this forward.
The immediate ask
Call Barrow & Grimm and ask about contributing to the Inola smelter legal fight.
(918) 584-1600Hear about hearings, public comment, and the next chance to show up.
Share this site with a neighbor and ask them to follow the updates.
Subscribe to DEQ notices so you don’t miss a comment deadline or hearing.
Facebook is where the campaign posts first.